Project Update: St Swithins, Stanley, Wakefield

It was great to achieve 45/45 on our recent Considerate Constructors audit at St Swithin's in Wakefield for Bridge Homes as part of the Efficiency North Framework.


The new homes are being completed through sectional completions with almost 30 handed over to date, and substructure, groundworks, brick and blockwork, flooring and internal finishes are currently ongoing on site. 